How value accumulates on the shop floor between issuing materials and receiving finished goods — and why the WIP balance so often will not reconcile.
Work in progress is the value sitting on the shop floor: materials issued to a work order, plus labour and overhead absorbed against it, minus the value of anything completed and received into stock. In an ERP the WIP account is a holding balance, and it should empty as orders close. A WIP balance that only grows is usually the clearest signal that something in manufacturing accounting is wrong.
WIP is where manufacturing costing goes wrong quietly. Every other balance has somebody watching it: stock gets counted, debtors get chased, the bank reconciles. WIP sits between those, often unreviewed, and absorbs the consequences of every under-issue, over-issue and un-closed work order until year-end stock valuation forces the question.
Components move out of stock and into the work order. The inventory account is credited, WIP debited.
Shop-floor confirmations against routing operations absorb labour and overhead onto the order at the rates configured.
Finished items are received into stock at standard cost. WIP is credited by that amount.
Any residue left in WIP after completion is the variance — it is cleared to a variance account, and this is the step most often skipped.
Open order value in the sub-ledger should equal the WIP account in the general ledger. If it does not, the difference is a real problem, not a rounding issue.
A manufacturer notices its WIP balance has climbed from about 18 lakh to 31 lakh over eighteen months, while production volume is flat. Nobody can explain it, and each month it gets a little worse.
The cause turns out to be ninety-one works orders left technically open — production finished, the goods were delivered, but nobody closed the order. Each one holds a small residual: material issued and not consumed, labour booked after the last completion, overhead absorbed on a final operation. Individually they are a few thousand rupees. Together they are roughly thirteen lakh of cost sitting on the balance sheet that belongs in cost of goods sold.
The fix is procedural rather than technical: a weekly review of orders completed but not closed, with a hard rule that an order cannot stay open more than thirty days past its last completion. The thirteen lakh comes out as a one-off correction, which is uncomfortable, and then WIP tracks production again. The useful lesson is that WIP is a holding account — the only thing it should do over a steady period is stay roughly steady.
| Term | What it means |
|---|---|
| WIP account | The balance sheet account holding the value of production that has started but not finished. It should clear as orders complete. |
| Absorption | Applying overhead to production, usually by labour hour or machine hour, so a unit carries a share of indirect cost. |
| Variance | The gap between standard and actual cost. Useful when it is analysed by cause; meaningless when it is written off in one line. |
| Order close | The point at which a works order stops accepting cost and its balance is cleared out of WIP. Orders left open are the main cause of WIP drift. |
| Backflush | Consuming components automatically on completion rather than issuing them individually. Fast, and dangerous when the BOM is inaccurate. |
An order left open holds its residual value in WIP forever. A list of orders completed but not closed is the first thing to check when WIP climbs.
Material taken from stores without being issued to the order understates WIP and overstates the variance later.
Labour absorbs at the routing's standard time. If the routing says twenty minutes and the job takes an hour, every order absorbs wrongly.
WIP should be reconciled monthly. Discovering a year of drift at the annual audit is the expensive version.
| Metric | What it tells you | What distorts it |
|---|---|---|
| WIP ageing | How long value has been sitting in WIP. Anything past one production cycle deserves a reason. | Averaging; a few very old orders disappear into a mean dominated by current ones. |
| Orders completed but not closed | The most direct leading indicator of WIP drift. | Nothing, which is why it is the one to watch weekly. |
| Variance as a share of standard cost | Whether standards reflect reality. Persistently large variance means the standard is wrong, not production. | Netting favourable against unfavourable, which cancels two real problems into one apparent non-problem. |
| Overhead absorption rate vs actual | Whether you are over- or under-absorbing, and therefore whether unit costs are believable. | Volume changes; a rate set at one output level misleads at another. |