Percentage-of-completion revenue recognition

Recognising revenue as a long contract progresses — and the estimate the whole method rests on.

In short

Percentage of completion recognises revenue on a long-running contract in proportion to progress, rather than at delivery. Progress is commonly measured cost-to-cost: costs incurred divided by total estimated costs. Recognised revenue is that percentage of the contract value, with the difference from amounts billed appearing as over- or under-billing.

Why It Matters

Why this matters in practice

For a contract spanning several periods, recognising everything at completion makes the accounts useless in the meantime. Percentage of completion spreads revenue across the periods in which the work happens. The weakness is that it depends entirely on estimated total cost — a figure produced by the people whose performance it reflects.

Revenue appears in the periods the work is done
Margin on long contracts is visible as it accrues
Over- and under-billing become reportable positions
Accuracy depends wholly on the cost-to-complete estimate
How It Works

How it works in practice

1

Establish contract value

The agreed revenue, including approved variations. Unapproved variations are a judgement and should be treated conservatively.

2

Estimate total cost

The critical input. Reviewed each period, by someone who can be challenged on it.

3

Measure progress

Cost-to-cost most commonly, though surveys of work performed or units delivered suit some contracts better.

4

Recognise revenue

Percentage complete applied to contract value, less revenue already recognised.

5

Report billing position

Recognised revenue compared with amounts invoiced gives the over- or under-billing to disclose.

Worked example

A worked example: why cost-to-cost can mislead early

A construction contract has a value of 5 crore and an expected cost of 4 crore. Three months in, cost incurred is 1.2 crore, so cost-to-cost gives 30 percent complete and revenue of 1.5 crore.

The difficulty is what that 1.2 crore consists of. If it includes 40 lakh of materials delivered to site but not yet installed, those materials represent expenditure rather than progress — the work they will become has not been done. Including them overstates completion and pulls revenue forward. Most standards require such costs to be excluded from the progress calculation for exactly this reason, and including them is one of the more common errors in practice.

Excluding uninstalled materials gives 80 lakh of progress cost, 20 percent complete and revenue of 1 crore. The 50 lakh difference is a real profit timing difference, and in an early period it can be the difference between a contract looking healthy and looking marginal. The general caution is that cost-to-cost is only as good as the definition of which costs measure progress.

Key terms

The vocabulary, briefly

Term What it means
Input method Measuring progress by resources consumed, such as cost incurred against total expected cost.
Output method Measuring progress by results delivered, such as units completed or milestones certified.
Over-billing Billing ahead of recognised revenue, which is a liability.
Under-billing Revenue recognised ahead of billing, which is a contract asset.
Onerous contract One expected to make a loss, which must be recognised in full immediately.
What Goes Wrong

Common mistakes worth avoiding

Estimates not revised

An estimate to complete left unchanged while costs overrun inflates recognised margin until the final period, when it collapses.

Including unapproved variations

Revenue recognised on a variation the client has not approved may never be collected.

Front-loaded costs distorting progress

Materials delivered early can make cost-to-cost overstate progress. Consider excluding uninstalled materials.

No independent review

The person estimating cost to complete is usually the person judged on margin. The estimate needs challenge.

What to measure

Numbers worth tracking

Metric What it tells you What distorts it
Percentage complete by method Comparing input and output measures. Large divergence means one of them is wrong.
Estimate at completion movement Changing total cost estimates, which retrospectively change every prior period's percentage.
Billing versus revenue position Over- and under-billing by contract, which is the balance sheet consequence.
Contracts in expected loss Onerous contracts, which must be recognised in full as soon as they are identified.
FAQ

Questions we are asked about this

For contracts spanning multiple reporting periods where progress can be measured reliably. Where it cannot, recognising on completion is the more defensible treatment.
Invoicing ahead of work performed — common with milestone billing. It is a liability, not revenue, and should be disclosed as such.
When the applicable standard's criteria for recognising revenue over time are met — broadly, where the customer controls the asset as it is created, or the asset has no alternative use and there is an enforceable right to payment for work completed. The criteria are specific and the assessment is contract by contract. This is an area where accounting advice on your actual contract terms is worth more than any general description.
Whichever more faithfully reflects the transfer of control. Output methods such as certified milestones are generally more reliable where they exist, because they measure results rather than effort. Cost-to-cost is widely used because it is practical and auditable, but it measures input and can be distorted by inefficiency, by uninstalled materials and by front-loaded costs. Whichever you choose, apply it consistently and document why.
It is treated as a change in accounting estimate, applied prospectively through a cumulative catch-up in the current period rather than by restating prior periods. The practical consequence is that a significant increase in expected total cost reduces the percentage complete, which reduces cumulative revenue, which produces a negative adjustment in the current period. This is why honest, timely estimate revision matters — deferring it concentrates the pain.
It does not, directly, and conflating the two is a frequent management error. Revenue recognition and billing are separate: you can recognise revenue well ahead of billing, or bill well ahead of recognition, and neither tells you anything about when cash arrives. Long-duration contracts need cash forecasting against the billing and collection schedule specifically, not against the revenue profile.
Related

Where to read next

What is project costing?

Read more

What is period close?

Read more

What is sub-ledger accounting?

Read more

Need this applied to your own systems?

We build and support the systems this page describes. Start with a free working proof of concept — no cost, no commitment.